Method 04
Wall saw cutting in Abu Dhabi, Dubai & Al Ain
Track-mounted diamond sawing for rectangular openings in reinforced concrete walls, cores and shafts. Straight edges, square corners, no overcut on the far face.
What it is
When to specify wall sawing
Wall sawing runs a diamond blade along a rail track bolted to the concrete face. Because the track holds the line, the cut is straight over its full length and the corners are square, which is what separates a saw cut opening from one broken out with a breaker and made good afterwards.
This is the method for door openings, window openings, lift shaft penetrations, stair core openings and any rectangular hole in a wall that has to look deliberate. On a fit-out programme in Business Bay or on Abu Dhabi island, wall sawing is usually the difference between a clean handover and a plastering bill.
Depth is the main constraint. A single pass reaches around 800 mm, and cutting from both faces roughly doubles that where access allows. If the wall is thicker than the blade can reach from either side, wire sawing takes over and we will say so at survey rather than after mobilising.
Applications
What we use it for
Door and window openings
New openings formed in existing RC walls, cut to the exact size on the architect's drawing with square returns.
Lift and service shafts
Openings through core walls for lift doors, riser access and builders work, cut on live buildings at night.
Stair core alterations
Landings and stair core walls opened for new access routes, with propping designed before cutting begins.
Wall removal in sections
Full wall panels cut into liftable sections, removed and cleared rather than broken out in place.
Ventilation and louvre openings
Precise rectangular penetrations for AHU, extract and louvre installations at height.
Expansion and control joints
Straight cuts through existing walls to form movement joints where structural movement requires it.
Sequence
How the job runs
Survey and prop check
Access, power and water confirmed, and the structural engineer's propping requirement agreed before anything is cut.
Scan the cut zone
GPR run over the full cut line to locate rebar, post-tension cables and embedded services.
Track and cut
Rail track anchored to the face, blade set to depth, cut run in passes with water fed to the blade.
Remove and clear
Sections segmented or craned out, opening edges dressed, slurry contained and waste taken off site.
Site control
Propping, sequence and structural sign-off
Cutting an opening in a loadbearing wall changes how load travels through the structure. Where the wall is structural, we will not cut until the structural engineer has issued a propping and sequencing requirement, and we build that requirement into the quote rather than treating it as your problem.
Sequence matters as much as the propping itself. A wide opening is normally cut in sections with props installed progressively, so the wall is never carrying its load across an unsupported span. On alterations to older buildings across Al Ain and Abu Dhabi, this is where most of the risk sits.
If you do not yet have engineer's drawings, say so at enquiry. We can cut to a marked-up sketch on non-structural blockwork immediately, but on RC we will ask for the sign-off first.